Culvert on the road

Reported via desktop in the Gully category anonymously at 09:35, Tuesday 16 June 2026

Sent to Aberdeenshire Council less than a minute later. Council ref: 969976.

Customer calling requesting to speak with the rods team about the culvert on the road. The culvert is all chocked with salt and mud. Customer calling to ask can it it be cleared out as looking to put drainage in for the water as flooding the farmhouse. As per customer request can they be called back to discuss the above and to organise a meeting with the roads team attending please.

Updates

  • We’ve had a look at the issue and have now passed your enquiry to our local Roads Team for assessment. They’ll determine what action is needed and we’ll update you once that assessment has taken place.

    Thanks again for taking the time to get in touch with us.

    In the meantime, you can find out more information on a range of topics on our website at www.aberdeenshire.gov.uk/roads-and-travel/roads.

    Posted by Aberdeenshire Council at 09:35, Tuesday 16 June 2026

  • Category changed from ‘Request for Advice or Information’ to ‘Gully’

    Posted by Aberdeenshire Council at 09:38, Tuesday 16 June 2026

  • We’ve had a look at the issue and we have now passed your enquiry to our local Roads Team to assess what can be done to resolve the matter. We’ll let you know when that assessment has taken place.

    Thanks again for your report

    State changed to: Action scheduled

    Posted by Aberdeenshire Council at 10:39, Tuesday 16 June 2026

  • State changed to: Internal referral

    Updated by Aberdeenshire Council at 12:28, Friday 26 June 2026

  • We’ve had a look at the issue and we have now passed your enquiry to our local Roads Team to assess what can be done to resolve the matter. We’ll let you know when that assessment has taken place.

    Thanks again for your report

    State changed to: Action scheduled

    Posted by Aberdeenshire Council at 17:35, Friday 26 June 2026

  • We’re currently developing our approach to displaying priorities and target completion times to keep residents better informed. In the meantime, we’ll continue to assess the level of risk and allocate resources based on urgency, location, and the availability of repair teams.

    This defect has been added to our works programme and will be scheduled accordingly.

    • To be Completed by: TBC
    • Road category: 4A
    • Road speed limit: 60

    The date shown above represents the latest target for completion based on our current programme of works. This may be brought forward where resources, operational priorities, or coordination with other activities allow. Defects assessed as posing a higher risk are prioritised for earlier repair whenever possible.

    Thank you for your patience while we carry out this work.

    State changed to: Planned

    Posted by Aberdeenshire Council at 17:57, Friday 26 June 2026