Potholes and poor surface from around library to Arduthie Road

Reported via desktop in the Pothole category anonymously at 14:00, Wed 3 December 2025

Sent to Aberdeenshire Council less than a minute later. Council ref: 936612.

The poor surface quality and potholes were given a temporary repair a few months ago but have already returned and are rapidly getting worse. This is a busy road and traffic is already having to swerve to avoid some of them

Updates

  • Thank you for letting us know about this issue. We will now investigate and provide you with an update within the next 7 days.

    You can find out more about our road maintenance on our website at www.aberdeenshire.gov.uk/roads-and-travel/roads/maintenance.

    Posted by Aberdeenshire Council at 14:00, Wed 3 December 2025

  • We’ve had a look at the issue and we have now passed your enquiry to our local Roads Team to assess what can be done to resolve the matter. We’ll let you know when that assessment has taken place.

    Thanks again for your report

    State changed to: Action scheduled

    Posted by Aberdeenshire Council at 19:16, Sun 7 December 2025

  • We’re currently developing our approach to displaying priorities and target completion times to keep residents better informed. In the meantime, we’ll continue to assess the level of risk and allocate resources based on urgency, location, and the availability of repair teams.

    This defect has been added to our works programme and will be scheduled accordingly.

    • To be Completed by: 14/11/2026
    • Road category: 3A
    • Road speed limit: 30
    • No of Potholes Recorded: 3
    • Maximum Pothole Depth: 40mm - 100mm
    • Maximum Pothole Width: 200mm - 400mm

    The date shown above represents the latest target for completion based on our current programme of works. This may be brought forward where resources, operational priorities, or coordination with other activities allow. Defects assessed as posing a higher risk are prioritised for earlier repair whenever possible.

    Thank you for your patience while we carry out this work.

    State changed to: Planned

    Posted by Aberdeenshire Council at 12:59, Tue 9 December 2025

  • We’ve issued this work out to one of our crews - we’ll let you know when the job is completed.

    • Scheduled to Start: 30/12/2025

    State changed to: In progress

    Posted by Aberdeenshire Council at 16:36, Thu 18 December 2025

  • State changed to: Fixed

    Updated by Aberdeenshire Council at 11:37, Tue 30 December 2025

This report is now closed to updates from the public. You can make a new report in the same location.